Clarington TS is a 500/230 kilovolt (kV) transformer station connected to the 230 kV and 500 kV transmission lines in the​ area. The project was completed and placed in-service on April 30th 2018

image of Transmission towers in a corridor strung with high-voltage powerlines

Project Timeline

  • JUL2014-SEP2015
  • Site preparation activities including the relocation of 230kV and 500 kV lines

     ​

  • JUL2015-FEB/MAR2017
  • Clarington TS Construction

  • NOV2015-AUG2017
  • 230 kV & 500 kV Lines Connection Preparation

  • AuG/SEP2016-Aug2017
  • ​Station Equipment Testing and Commissioning

  • AUG2017-MAR/APR2018
  • ​230 kV & 500 kV Lines Connection​

  • MAR-APR2018
  • Clarington TS - In-Service​​​

  • APR/May2016-May/JUN2019
  • ​Habitat Creation and Visual Screening

Project Approvals

Learn more about the Environmental Study Report (ESR) we completed to support the Clarington Transformer Station project.

Project Approvals
Public Consultation

Learn more about the Public Information Centres (PICs) we conducted to support this project.

Public Consultation

Project Resources

View maps, diagrams, and resources related to this project.

Project Resources
Community Liaison Committee

Learn more about the committee we established to support and encourage community participation on this project.

Community Liaison Committee

Contact Us

 

For more information or to be added to the project contact list, please contact:​​

Community Relations
Hydro One Networks Inc.

Tel:  416-345-6799 or 1-877-345-6799

Fax: 416-345-6984

Community.Relations@HydroOne.com